Back

Why don’t some Add Item buttons appear in the Construction bill of quantities?

The system prevents additions that break the table structure: an item that has Work Items under it accepts only Work Items, an item that has Sub items under it accepts only Sub items, and a Sub item at the third level accepts only Work Items. Under a Work Item, you can add Materials/labor only in the Cost Sheet, and nothing can be added under a Material.

  • If only one type is allowed, the + button adds it directly without showing a menu.
  • The Add button at the Bottom of the table always adds a Main Tender.
  • To reorganize, drag items under another parent at the same level.

🛈

Note: The Report states that the buttons appear dimmed; in the code, an option that is not allowed does not appear at all.

Why is there no Material/labor button in an Estimate, Contract, or Bid?

Materials and labor are part of the Cost calculation, and they belong only in the Cost Sheet. The quantities table of an Estimate, Contract, or Bid includes Main items, Sub items, and Work Items, and nothing can be added under a Work Item. To price Materials, create a Cost Sheet and link it to the Estimate.

  • Cost Sheet: Main Tender, Sub item, Work Item, Material/labor.
  • Estimate, Contract, and Bid: Main Tender, Sub item, Work Item.
  • When you use Create Estimate from a Cost Sheet, the items are transferred without the Materials/labor, and their Cost is reflected in the Price of the Work Item.
  • The + button does not appear next to a Work Item in an Estimate or Contract.